E&G Funded Capital Renewal

View Past E&G Renewal Portfolios

Building Preservation - $3 million Mechanical Electrical and Plumbing Systems - $1.17 million Fire and Life Safety Systems - $830,000
  • Roof replacement on Agriculture & Life Sciences Building
  • Burt Hall South roof replacement (approved this fiscal year, scheduled for spring 2019)
  • Roof replacement on 4575 SW Research Way (building purchased 2018)
  • Pharmacy chiller replacement
  • Owen Hall HVAC replacement design
  • Building controls replacement in Pharmacy, Cordley, Wilkinson and Burt Halls  
  • Kerr Administration Building fire alarms 

 

Building Preservation - $3.5 million Mechanical Electrical and Plumbing Systems - $5.3 million Reserves - $1 million
  • Roof replacement on Magruder Hall
  • Roof replacement on Oak Creek Building 
  • Roof replacement on Burt Hall 1 
  • Gilbert Hall chiller replacement
  • Owen Hall chiller, cooling tower and direct digital control replacement
  • Pharmacy Building general purpose classroom 305 chiller replacement
  • Unity HVAC controls for 4 or 5 building (to be determined)
  • Building controls for Agriculture & Life Sciences Building

 

Mechanical Electrical and Plumbing Systems - $11.6 million Fire and Life Safety Systems - $1 million E&G Funds Trade - $1.7 million Reserves - $695,000
  • Cordley Hall renovation
  • Agricultural and Life Sciences Building hyperchill process water chiller 
  • Radiation Center chiller replacement
  • Withycomb Hall electrical service upgrade
  • Nash Hall laboratory chilled water system
  • Fairbanks Hall Seismic Safety
  • E&G funds traded with State bond funds to reach $100,000 capitalization threshold on smaller, state-wide facilities

 

Capital Renewal as part of Major Projects ($7M)
  • Withycombe East Renovation - Dairy Processing Facility ($3m) - part of the $20m project

  • McAlexander Renovation ($4M)

COVID-19 impacts to the university allowed OSU to roll up $37M in unspent funds for capital renewal.

  • LaSells Stewart Center Mechanical and Roof replacement ($800,000)
  • Cordley Hall Renovation ($7.5M)
  • Fairbanks Hall Renovation ($5.7M)
  • Campus Operations Center project ($3.2M)
  • HMSC Seawater ($600,000)
  • West Greenhouse expansion ($3.3M)
  • Milam Hall roof ($1M)
  • Wiegand Hall window replacement ($1.6M)
  • Oak Creek Greenhouse expansion ($1.5M)
  • Library archives and Research Way Building ($1.4M)
  • Radiation Center HVAC ($800,000)
  • District Utility Plant ($800,000)
  • Energy Turbine ($1M)
  • Community Hall Slope ($600,000)
  • Statewide Research ($2.1M) 
  • Other smaller projects

Below is a list of capital renewal initiatives for which we received $6.6 million in E&G funding for FY23.

Building Renewal ($6.6M)
  • Withycombe East Renovation - Dairy Processing Facility ($3M)
  • Plageman Hall Renovation Design ($1M)
  • Heat Plant/Benton Place Design ($2.5M) 
Unrestricted Funds for State Capital Renewal ($1.5M)

Below is a list of capital renewal initiatives for which OSU used $12.3 million in E&G funding for FY24.

  • Withycombe Renovation ($4M)
  • Heat Plant Renewal ($2.5M)
  • Kelley Engineering Center District Utility Plant ($4.2M) 
  • Richardson Hall Midlife Renewal ($1.6M)

 

The E&G funded capital renewal projects are prioritized using the following criteria:

  1. Is this project critical for the building to operate and for people to have access?
  2. Will this project contribute to student, faculty and staff success?
  3. Are there other matching funds available for this project?